Closing a project

Clear the Close-out checklist of unbilled time, expenses, draft invoices and milestones, close the project, and save it as a template.

What you'll achieve

Close a finished project with nothing left unbilled, and reuse what it taught you.

You'll end up with: A closed project nobody can add time, expenses or invoices to, and, if you like, a template from it.

Before you start

Keep the project on track, last step. A project that's never closed keeps collecting stray time and costs, and its margin keeps moving. Closing it stops that. Close-out first checks that nothing billable is left behind, so you don't close a job with money still on the table.

We'll use Meridian Studio, the demo practice, and close Cedar Row Apartments. It still has unbilled time, expenses, draft invoices and claimable milestones, so you'll see what an open line looks like.

Check what's left

  1. 1

    On the project, click Close project… in the top bar, next to Pause. The page switches to its Close-out view.

  2. 2

    Before you close lists Unbilled time, Unbilled expenses, Draft and approved invoices, Unbilled milestones and Unpaid invoices, each with a live count. On Cedar Row Apartments, Unbilled time reads 21h, $3,885.00.

  3. 3

    Use each line's action, New invoice, See expenses, See invoices or Open the schedule, to clear it.

  4. 4

    Beside the list, the Close-out report shows how the job ended: dates, duration, and each stage's hours against plan, its fee and what was billed.

Close it

When the list is clear, click Close project and confirm. If something is still open, the button reads Close anyway and asks you to confirm. Once closed, no one can add time, expenses or invoices to the project. Reopen project undoes it. Cedar Row Apartments has four lines open, so we click Close anyway and confirm.

You'll know you're done when the page says This project is closed.

Reuse it

Under the report, Save as template starts a project template with the project's stages, fees and team, so the next job like it starts from real figures.

Troubleshooting

  • The billing checks are missing. They need financial access to the project. Ask someone with it to check them.
  • Someone needs to log late time. Reopen the project, let them log it, and close it again.

Where this fits next

That's the end of the project lead's track. The bookkeeper's track picks up billing in Bill clients and get paid.